Bridgeville Borough’s 2026 Road Program is officially underway! Youngblood Paving Co., on behalf of the Borough and the Bridgeville Parking Authority, will begin resurfacing several streets starting today.
Project Schedule:
• Parking Lot #2 (corner of Washington Avenue and Bank Street Extension) will be closed this week, as posted, for milling and resurfacing.
• Lurry Street: Milling and paving operations begin today. Access will be restricted while work is underway.
• Sarah Street and Missouri Avenue: Beginning Tuesday and continuing through project completion, crews will perform milling, concrete curb repairs, and paving. Traffic will be limited to local residents during construction.
We appreciate your patience and cooperation as these improvements are completed. Please use caution when traveling through work zones, follow all posted signs, and watch for construction crews and equipment.